March 2005
|
Design team appointed
|
|
July 2005
|
Main contractor appointed - Stage 1
|
|
Dec 2005
|
Detail design report
|
|
March 2006
|
Planning Permission received / Main contractor appointed - Stage 2
|
|
May 2006
|
Main works start on site
|
|
- Sep 2006
|
Demolition of 8th floor / roof
|
|
- Feb 2007
|
Demolition complete
|
|
- Mar 2007
|
Precast concrete beams to auditorium
|
|
- Jun 2007
|
Start of Mechanical and Electrical works
|
|
- Jul 2007
|
Steel completion
|
|
- Sep 2007
|
Topping Out Ceremony
|
|
- Oct 2007
|
Commence internal partitions
|
|
- Oct 2007
|
Building water tight
|
|
- Nov 2007
|
Scaffold removal
|
|
- Dec 2007
|
Electrical power on
|
|
- April 2008
|
Commence M & E services commissioning
|
|
- May to Jul 2008
|
LSE fit out of IT comms. room and telecoms
|
|
July 2008
|
Practical completion
|
|
Aug-Sep 2008
|
Migration into new building
|
|
October 2008
|
Commencement of new academic year - building fully up and running
|