Development timetable

March 2005

Design team appointed

July 2005

Main contractor appointed - Stage 1

Dec 2005

Detail design report

March 2006

Planning Permission received / Main contractor appointed - Stage 2

May 2006

Main works start on site

- Sep 2006

Demolition of 8th floor / roof

- Feb 2007

Demolition complete

- Mar 2007

Precast concrete beams to auditorium

- Jun 2007

Start of Mechanical and Electrical works

- Jul 2007

Steel completion

- Sep 2007

Topping Out Ceremony

- Oct 2007

Commence internal partitions

- Oct 2007

Building water tight

- Nov 2007

Scaffold removal

- Dec 2007

Electrical power on

- April 2008

Commence M & E services commissioning

- May to Jul 2008

LSE fit out of IT comms. room and telecoms

July 2008

Practical completion

Aug-Sep 2008

Migration into new building

October 2008

Commencement of new academic year - building fully up and running