Timetable

Timetable 478x221jpg

Outline Programme for the Centre Buildings Redevelopment

Key dates:

  • Planning application submitted to Westminster City Council in December 2014
  • Planning permission received on 8 April 2015
  • Demolition started June 2015 and completed December 2017
  • New building is expected to be finished April 2019

Cantillon were appointed as the demolition contractor and Mace Group as the main construction contractor.

More detail on the programme and implementation plans will be provided as the project progresses.

 